Maffitt Lake Road Construction Update - 5/2/18

Post Date:05/02/2018

Grimes Asphalt and Dallas County crews finished the pavement widening portion of the project today.  No additional work will be performed until Monday, May 7th.

On Monday, Contractors will begin cracking and seating the existing concrete pavement and paving the length of the project, with the exception of the final layer of asphalt.  We anticipate this work to be completed in one week, depending on weather.  The ride quality will be greatly improved by the end of next week.

Upon completion of this first phase of construction we anticipate a 2 week delay while we wait for utility companies to finish their relocation work.

The last phase of construction will be the installation of drainage tile along the edge of the new pavement, placement of the final layer of asphalt, repaving of drives, and placing pavement markings.  This last phase is anticipated to take approximately two weeks, depending on weather.

Thank you for your continued patience as we move closer to finishing this project.

Please visit Current Dallas County Road Closures for information about road closures and detours relating to Dallas County Road Department Projects.

Sign up for eNotifications related to Dallas County Road Department projects.

Questions about this project may be directed to the Dallas County Road Department at 515-993-4289